English Manual: Super Power Series 60-80 25/03/2004
2
1 GENERAL INSTALLATION GUIDELINES
Determining the most efficient position for your thruster:
The tunnel should be placed in the deepest section of the hull and as far forward as possible.
For maximum efficiency the tunnel should be installed no less than 100 mm from the water
line.
Where the boat’s design will not allow for this submersion, any subsequent efficiency deficit
can be partly compensated using a position closer to the bow (to create greater leverage).
Decide on the most suitable configuration for both the tunnel and the electric motor.
Where necessary, the weight of the electric motor should be supported and its position
secured.
The propeller should be centred in the tunnel and should not, under any circumstance,
protrude from the opening.
Water Line
185 mm
As far forward as possible
Support
The area around the thruster should remain accessible, dry and ventilated.
The thruster can draw power from either the starter or auxiliary batteries, but use of the
source closest to the thruster is recommended.
2 TUNNEL
When the final tunnel position is determined (and all dimensions have been checked), mark the
centre of the tunnel’ position and drill a Ø 10 mm hole. Make up a metal compass from 8 mm
rod.
Do not
stratify over
this zone
Do not
stratify over
this zone
Fit compass in to the Ø 10 mm holes and trace the form of the tunnel on to the hull
(elliptical).
After cutting out the elliptic hole , disc the interior surface of the hull, by approx. 10 to 15 cm
around the holes.
The outside surface of the tunnel is then ready to be fibre-glassed.